When should change orders be issued?

Prepare for the Florida Electrical Business Exam. Study with quizzes, flashcards, and detailed explanations. Ace your exam!

Change orders should be issued whenever there is a change in the project scope or costs. This ensures that all parties involved in the project are in agreement regarding any modifications that affect the original contract terms. Change orders serve as formal documentation that outlines what changes are being made, the reasons for those changes, and any adjustments to costs or project timelines. By following this process, contractors can protect themselves and clients from misunderstandings, ensuring that expectations are clear and well documented throughout the duration of the project. This practice helps maintain legal clarity and financial accuracy, which are essential for a successful business operation in electrical contracting or any related field.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy